Framing Continued
Plat #4, Lot #9  in White Horse Subdivision - 5187 W. 150th Place, Leawood Kansas 66224 (East of Nall and 151st)

(return)

 10/28/02 - Steel Framing Begins by erecting the walls. The steel bottom plate was placed 10/26/02
 10/28/02 - Steel Framing erecting the walls continues.
10/29/02 - Steel Framing continues, main level 10" floor joists.
10/31/02 - Main level flooring secured to joists.
11/1/02 - Steel Framing erecting the walls continues on the main level.
11/1/02 - Steel Framing erecting the walls continues on the main level.

Roof on entrance goes up.

11/6/02 - Steel Framing erecting the walls continues on the main level.
11/7/02 - Steel Framing erecting the walls continues on the main level.
(return)