Framing Continued
Plat #4, Lot #9 in White Horse Subdivision - 5187 W. 150th
Place, Leawood Kansas
66224 (East of Nall and 151st)
(return)
| 10/28/02 - Steel Framing Begins by erecting the walls. The steel bottom plate was placed 10/26/02 | ![]() ![]() |
| 10/28/02 - Steel Framing erecting the walls continues. | ![]() ![]() |
| 10/29/02 - Steel Framing continues, main level 10" floor joists. | ![]() ![]() |
| 10/31/02 - Main level flooring secured to joists. | ![]() |
| 11/1/02 - Steel Framing erecting the walls continues on the main level. | ![]() ![]() |
|
11/1/02 - Steel Framing erecting the walls continues on the main
level.
Roof on entrance goes up. |
![]() ![]() |
| 11/6/02 - Steel Framing erecting the walls continues on the main level. | ![]() ![]() |
| 11/7/02 - Steel Framing erecting the walls continues on the main level. | ![]() ![]() |